And now an apology…

Guess who missed out a chunk of work in the summary in the last blog? In case you need reminding, I had said we need only fit four Velux windows and do a little bit of woodwork, and we could then work on fitting the roof.

Sadly, in my excitement, I forgot that we hadn’t yet finished the front and side walls. Grrrr. So this week we have been finishing creating the wall carcassing (the rough structure), adding plywood, and then putting Tyvex across the exterior plywood.

Below you can see how the wall at the front of the dormer was a bit see-through…

…so (below) we have added studs and noggins to make it all rigid, and then we fit plywood over this structure and…

…then covered it with Tyvex fabric followed by battens which will eventually support cement board and render.

Nothing to worry about – this will just add about another week’s work before we can move on to finishing the roof. I am finding this delay stressful because the lack of rain for about the last month means it is all quite dry now, and we would like to keep it that way by fitting the roof! Sadly, there is a chance of thunderstorms on Sunday in which case all will get wet! Also, we have heard from the company providing the fire stop that belongs under the roof that their delivery is delayed until late May, so we may yet have to come up with an unorthodox solution should the weather threaten to break. More news next time!