And now we start creating the first floor…

When I last wrote, we had cut the wall plate to size, and awaited dry weather to lay it in place on a bed of mortar. Below you can see it wasn’t raining, so the first section has been mortared in place and below that…

…the second section has been laid, which butts up to…

…the block wall at the front of the suites. Clearly, this block wall needs to be a little higher so we set too and…

… voila, here it is now.

With the wall plate in place at floor level, we could start building one section of the stud walls. We completed two sections horizontally, and then turned the structure up, and later around to put it in place…

…as the noggins in the right hand section needed to be cut to fit precisely. I was on cutting duties and Mike on fitting…

…most of the time, anyway! We do like to each have a go at all the jobs – well, most of them anyway.

Once that section of stud wall was complete, we turned our attention back to the block wall. First, we fit the remaining insulation to the inside of the wall…

…and then carefully measured the wall in various places so that we could work out exactly where the wall plate should sit.

Below you can see the wall plate now in position, sitting on damp proof membrane, drilled and bolted in place with studding and sitting on a bed of mortar.

We were very lucky to have a sunny couple of half-days last week to work in. The next sunny day should be with us soon, and I will be sure to let you know how we progress this building when that happens!!