Three out of four nearly ready…

…for the next stage, but in the meantime we are still preparing to bring in the first fit. Below you can see us adding wood to the block wall to level it out, ready for us to secure the visqueen around the French doors.

We then squeezed the soundproofing sealant into the joint where the centre wall meets the block wall and…

…whilst Mike did that, I took advantage of a still and dry day to paint the fire door, inside and out, and when Mike had finished with the sealant…

…he blocked up the bathroom window. In our original plans, we installed lintels and left holes for windows for the downstairs bathrooms. Our second designer noticed these were too close to where the fire escape stairs will be, and were a fire risk – so we are now blocking them up.

Once that was done, we insulated the timber front wall and then…

…turned the corner to the side wall. We covered and insulated the timber portion and then…

…added the battening, to which plasterboard will eventually be attached.

This left us with the remaining block wall to cover.

On the back wall of what will become the bathroom, we needed to be careful not to damage the foul water pipe…

…and I hope on our next posting to be able to show we have finished covering this wall, and moved on to the fourth of four areas – because, frankly, I think we are both getting a bit bored with this!!

Any one for more insulation?

The weather for the last couple of weeks has suited indoor working, so we are back on insulation. Below you can see Mike attaching insulation over the stairwell This has been delayed as we work in the stairwells standing on a temporary platform of three rafters and a plywood floor which we had left stranded in the wrong building, so after moving it back, here we go…

…and then we returned to the ground floor and put in a few more studs for the walls as they butt up to the external wall. Between the stud and the blocks, we have some visqueen damp proof membrane…

,,,which we will be installing along all of the block wall. Once the end stud and visqueen were in place we could…

…start adding the plywood to stiffen the bathroom walls / make it easier to attach items to the bathroom walls and then …

…we moved towards the back of the building. We had to remove the old plaster as we needed the wall to be smooth: this took a surprising amount of effort! Much of this was removed two years ago and only the stubborn bits remained – and I can tell you the bits were still very stubborn. Once chipped away a tiny piece at a time, we stretched the visqueen over the wall and…

…insulated the gap in the steel, cleaned the rubbish out of the visqueen at the base of the wall (which has been waiting for us since we cast the concrete floor in 2023) and tucked the new plastic into the old plastic and…

…began to fix all in place with battening.

My job was to cut the battens to size and, when Mike was fitting them, to…

…remove the stubborn plaster on the next wall we needed to cover before we got there. Once that wall was cleared we returned to the battened lot and added the next sheet of visqeen and more battening.

We haven’t quite got on to the insulation – that will be featured in my next post…

Progress – and smugness – what a combination!

We were still waiting for some dry weather so we can paint the windows and doors. As you can guess, the weather was wet so we were covering the block wall in the left hand upstairs room with the waterproof fabric and then…

…returned to putting the battening over the insulation already in place…

…so we had got to the situation where all the insulation is in place, but some battening is missing… because we had used all of our supplies! So it was time for a change…

…and we moved to the right hand suite, downstairs, and found we needed to move a lot of things around to clear a space to work in -which is about par for the course for Mike and I!

To be honest, most if the insulation is now piled up behind the camera, but ahead you can see the space where some stud walls need to go…

…but before we can attach the stud walls to the block walls, I need to remove the last of the old plaster. I took the easy bits off about 18 months ago, and so you may notice the concentration on my face as I try to shift the stubborn bits ready for later.

When we felt ready, we pulled out the plans to work out where the walls need to go, only to find to our horror that the drain point (which we put in years ago, using our first designer’s drawings) would have been in the hallway if we built the walls as specified by our new designer – so we cut some pieces of wood to size and shuffled them about on the floor until we came up with a pattern (as below) that allowed the drain to be in the bathroom, but also leaving a wide enough hallway that a wheelchair can go through it. And yes, that was quite a stressful few hours whilst we worked this out!

After photographing our layout and getting approval from our designer, we started screwing the floorplates to the concrete floor using some extremely whizzy screws…

…and once that was done, we attached a second layer of floorplate (we will explain why in a few months time) and then started adding the studs…

…so that you can begin to see how this floor will work. Beyond the 3 studs will be the bedroom; the enclosed arear in front of the 3 studs will be the wet room; there will be hallway to the left of the single stud at the front; and Lola is sitting in the kitchen area.

Below you can see the view from the bedroom, through the wetroom, and Lola, remarkably, is still sitting where the L-shaped kitchen will go. Mike is standing in what will become the living area.

And such is our forward planning that, at this point, we took delivery of more battening, but ran out of ‘4 be 2 be’ so had to stop building the walls.

We had guests in this weekend, but today – unusually – we left all the hospitality work on hold because no rain was forecast, so we have finally finished painting the outside of all our windows, and all but one door. And, let’s be honest, we are both feeling pretty smug tonight, which feels pretty good!