Last week we continued to put Aquapanel on one of the external walls – which required us to slate the base of the left hand side of the wall as described on our last blog, when we did the right hand side. Here you can see Mike carefully measuring the height of Aquapanel needed, given we have to overlap the lead flashing by the required amount. And then the weather changed so we…

…returned to working inside the building! Below you can see us cladding the stanchions (which takes up a surprising amount of time and effort) with very thin insulation, followed by fire board (to protect the steel stanchion in the event of fire), followed by…

…the vapour barrier, after which we were able to fit…

…the plywood to the external walls on either side and and then put 50mm of insulation on either side of the stanchion, and then across the front of the stanchion…

…so that the external wall is now ready for fireboard to be installed in due course. Throughout the timber-framed part of the building, we will be using fireboard rather than plasterboard for safety reasons – but more of that (considerably) later!

The pictures above show us working on the main bathroom for the first floor: below you see us working on the shower room for the ‘back’ bedroom, where we are repeating the same actions. Below you can see insulation on the stanchion with us starting the fireboard which will soon be covered by the vapour barrier and plywood.

The picture below shows the progress so far on the left hand wall, which has stalled temporarily whilst we try to locate further supplies of Aquapanal! Who knows what we will do next…?!

Once again we are in the time of year when we are busy with guests and the building work has to take something of a back seat, so please don’t be too disappointed if our progress slows a little…