To recap – last week we had put this piece of wall late in place and had prepared the next piece but…

…had run out of cavity stop so had to wait until they (the green stuff) arrived. Below you can see I have filled the cavity and am now spreading mortar ready for us to…

…put that next piece of wall plate in place. Now that this corner entire is ready to go, we were able to…

…re-start building the first floor back wall of the suites. We carefully used multiple studs to form the fire stop on the back wall between the two suites and then we…

…just kept building that wall.

Having got to the end, Mike made sure all was stabilized, and then we started putting in the lower level rafters…

…which are supported on the first steel. By the end of the first day we had got to here…

…by early afternoon on the second day we were here. We then had to deal with a little problem that we had recently noticed:

Below is the end of the top rail of the back wall, protruding about 300mm beyond the side wall, so that the roof can overhang the side of the building. But if you look back towards the steels you will see…

…we completely forgot to run the timber on the top of the steels 300mm beyond the end of the steel. Oops. Double oops, was we have forgotten this on two steels. Oh well, at least we noticed before we got any further! So here you see Mike cutting through the timbers…

…and when we begin the building work again next week, we will cut in some new timber at the appropriate length. Now that the weekend is with us, we are pleased to report we need to put our pinnies on and get back to the hospitality work until Monday rolls round. Here’s hoping next week’s weather is as building-suitable as last week’s.