So near, and yet still a way to go…

To remind you, we are trying to finish slating this roof by Christmas. Last Monday we started work with the roof looking like this…

…and ended with it looking like this. Our friends Julie and Yvonne arrived on Monday night and on Tuesday we all set to…

…and soon we were working much higher on the roof, which is hard to tell from these photos which were taken from ground level. We needed to do some complex thinking before slating above the small dormer so we worked this close and then…

…moved the scaffolding tower and started slating the left hand section of the roof. Things go so much faster when we have extra pairs of hands to move the slates up into position and so by end of Wednesday…

…we had slated until just below the top of the small dormer. At that point we needed to start working across the top of the dormer, but the battens on the left and those on the right of the dormer were put in at slightly different heights, so we needed to suck through our teeth as we worked out quite how to continue slating.

The answer came to us: we would continue slating across whilst the battens allowed, and then put additional battens in place when they were needed to support the slates properly. You may not be able to see: we have a taut piece of white string running above the slates on each side, enabling us to adjust the heights of individual slates as necessary…

…and then we put additional lead above the dormer, to ensure that any rain water is sent the right way, and would not drip under the slates!

…and by the end of yesterday, we had got to this stage.

Yvonne and Julie had to leave today to get on with their Christmas plans, so we have just a little little bit still to do before Christmas. Here’s hoping the weather stays dry for another day or two….